Simulation-based approach for Multiproject Scheduling based on composite priority rules

Alvarez-Campana et al.

This paper presents a simulation approach to enhance the performance of heuristics for multi-project scheduling. Unlike other heuristics available in the literature that use only one priority criterion for resource allocation, this paper proposes a structured way to sequentially apply more than one…

Street Traders Math 3.5 Rigor 8.0
More details
Authors
Pablo Alvarez-Campana, Felix Villafanez, Fernando Acebes, David Poza

On the project risk baseline: integrating aleatory uncertainty into project scheduling

Acebes et al.

Obtaining a viable schedule baseline that meets all project constraints is one of the main issues for project managers. The literature on this topic focuses mainly on methods to obtain schedules that meet resource restrictions and, more recently, financial limitations. The methods provide different…

Street Traders Math 3.5 Rigor 6.5
More details
Authors
Fernando Acebes, David Poza, Jose M Gonzalez-Varona, Javier Pajares, Adolfo Lopez-Paredes

Impact of aleatoric, stochastic and epistemic uncertainties on project cost contingency reserves

Curto et al.

In construction projects, contingency reserves have traditionally been estimated based on a percentage of the total project cost, which is arbitrary and, thus, unreliable in practical cases. Monte Carlo simulation provides a more reliable estimation. However, works on this topic have focused…

Street Traders Math 3.5 Rigor 6.0
More details
Authors
David Curto, Fernando Acebes, Jose M Gonzalez-Varona, David Poza

Beyond probability-impact matrices in project risk management: A quantitative methodology for risk prioritisation

Acebes et al.

The project managers who deal with risk management are often faced with the difficult task of determining the relative importance of the various sources of risk that affect the project. This prioritisation is crucial to direct management efforts to ensure higher project profitability. Risk matrices…

Street Traders Math 3.5 Rigor 5.5
More details
Authors
Fernando Acebes, José Manuel González-Varona, Adolfo López-Paredes, Javier Pajares

Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques

Acebes et al.

The aim of this paper is to describe a new an integrated methodology for project control under uncertainty. This proposal is based on Earned Value Methodology and risk analysis and presents several refinements to previous methodologies. More specifically, the approach uses extensive Monte Carlo…

Street Traders Math 3.5 Rigor 5.0
More details
Authors
Fernando Acebes, M Pereda, David Poza, Javier Pajares, Jose M Galan

Project Risk Management from the bottom-up: Activity Risk Index

Acebes et al.

Project managers need to manage risks throughout the project lifecycle and, thus, need to know how changes in activity durations influence project duration and risk. We propose a new indicator (the Activity Risk Index, ARI) that measures the contribution of each activity to the total project risk…

Philosophers Math 3.5 Rigor 4.5
More details
Authors
Fernando Acebes, Javier Pajares, Jose M Gonzalez-Varona, Adolfo Lopez-Paredes

Analisis cuantitativo de riesgos utilizando "MCSimulRisk" como herramienta didactica

Acebes et al.

Risk management is a fundamental discipline in project management, which includes, among others, quantitative risk analysis. Throughout several years of teaching, we have observed difficulties in students performing Monte Carlo Simulation within the quantitative analysis of risks. This article aims…

Philosophers Math 2.5 Rigor 3.0
More details
Authors
Fernando Acebes, David Curto, Juan de Anton, Felix Villafanez