Paper: arXiv 2406.00077
Authors: Fernando Acebes, David Poza, Jose M Gonzalez-Varona, Javier Pajares, Adolfo Lopez-Paredes
Abstract
Obtaining a viable schedule baseline that meets all project constraints is one of the main issues for project managers. The literature on this topic focuses mainly on methods to obtain schedules that meet resource restrictions and, more recently, financial limitations. The methods provide different viable schedules for the same project, and the solutions with the shortest duration are considered the best-known schedule for that project. However, no tools currently select which schedule best performs in project risk terms. To bridge this gap, this paper aims to propose a method for selecting the project schedule with the highest probability of meeting the deadline of several alternative schedules with the same duration. To do so, we propose integrating aleatory uncertainty into project scheduling by quantifying the risk of several execution alternatives for the same project. The proposed method, tested with a well-known repository for schedule benchmarking, can be applied to any project type to help managers to select the project schedules from several alternatives with the same duration, but the lowest risk.
Complexity vs Empirical Score
- Math Complexity: 3.5/10
- Empirical Rigor: 6.5/10
- Quadrant: Street Traders — practical and empirical, lighter on theory
Why this score: The paper introduces a novel practical framework for integrating aleatory uncertainty into baseline project schedule selection among equal-duration alternatives. It relies on simulation and empirical benchmarking rather than heavy mathematical derivations, making it a clear and applied operational research study.
Research Flowchart
flowchart TD
A["Research Goal: Select schedule with lowest risk among equal-duration alternatives"] --> B["Input: Benchmark Project Schedules PSPLIB & Aleatory Uncertainties"]
B --> C["Quantify Risk: Integrate aleatory uncertainty into alternative schedules"]
C --> D["Simulate & Evaluate: Run Monte Carlo simulations to assess deadline probability"]
D --> E["Select Baseline: Identify schedule with lowest risk & highest deadline compliance"]
E --> F["Outcome: Risk-aware schedule selection method applicable to any project"]
Cited References (93)
- Managing risk on projects (2009)
- Integrated Cost-Schedule Risk Analysis (2016) — link
- Managing Risk in Projects (2024) — link
- Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques — → 2406.02589
- Project configuration by means of network theory (2015) — link
- The Fit between Project Characteristics and Application Development Methodologies: A Contingency Approach (1999) — link
- Measuring Time: Improving Project Performance Using Earned Value Management (2009) — link
- Project Scheduling and Cost Control: Planning, Monitoring and Controlling the Baseline (2007)
and 85 more
- Empirical Perspective on Activity Durations for Project-Management Simulation Studies (2015) — link
- Reinventing project management : the diamond approach to successful growth & innovation (2007)
- Risk Analysis: A Quantitative Guide (2000)
- Risk management for SMEs: Tools to use and how (2006) — link
- Recent trends in solving the deterministic resource constrained Project Scheduling Problem (2013) — link
- PSPLIB - A project scheduling problem library (1997) — link
- On the dynamic use of project performance and schedule risk information during projecttracking (2010) — link
- Treatment of uncertainties in space nuclear risk assessment with examples from Cassini mission applications (1999) — link
- Engineering and contracting projects: A value at risk based approach to portfolio balancing (2007) — link
- Using extended Monte Carlo simulation method for the improvement of risk management: Consideration of relationships between uncertainties (2007) — link
- Project Risk Management: Processes, Techniques and Insights (1998) — link
- Qualitative risk analysis: some problems and remedies (2006) — link
- Modeling and risk analysis of virtual project team through project life cycle with fuzzy approach (2014) — link
- Management of construction cost contingency covering upside and downside risks (2014) — link
- Estimation and evaluation of uncertainty: a minimalist first pass approach (2000) — link
- A classified bibliography of recent research relating to project risk management (1995) — link
- Exploring the Influence of Seasonal Uncertainty in Project Risk Management (2014) — link
- Uncovering the trends in project management: Journal emphases over the last 10 years (2005) — link
- Defining uncertainty in projects – a new perspective (2007) — link
- Structural safety–issues and progress (2004) — link
- Scheduling subject to resource constraints: classification and complexity (1983) — link
- Evaluating methods of investment project and optimizing models of portfolio selection in fuzzy uncertainty (2011) — link
- A new approach for project control under uncertainty. Going back to the basics (2013) — link
- Exploring Monte Carlo Simulation Applications for Project Management (2007) — link
- Critical-path planning and scheduling (1959) — link
- Assessing and managing important risks (1999) — link
- Investigating differences among research projects and implications for managers (2005) — link
- A learning-based optimization approach to multi-project scheduling (2014) — link
- An extension of the EVM analysis for project monitoring: The Cost Control Index and the Schedule Control Index (2010) — link
- Developing a RAD standard (1995) — link
- Finance-Based Scheduling of Construction Projects Using Integer Programming (2004) — link
- Risk avoidance in bidding for software projects based on life cycle management theory (2006) — link
- Management of risks, uncertainties and opportunities on projects: time for a fundamental shift (2001) — link
- A project contingency framework based on uncertainty and its consequences (2009) — link
- Modeling activity times by the Parkinson distribution with a lognormal core: Theory and validation (2011) — link
- Application of a Technique for Research and Development Program Evaluation (1959) — link
- Key points of contention in framing assumptions for risk and uncertainty management (2006) — link
- A review of analytical models, approaches and decision support tools in project monitoring and control (2014) — link
- Context-Adaptive Agility: Managing Complexity and Uncertainty (2005) — link
- Project Management with Dynamic Scheduling: Baseline Scheduling, Risk Analysis and Project Control (2012) — link
- What’s Wrong with Risk Matrices? (2008) — link
- Goals-and-methods matrix: coping with projects with ill defined goals and/or methods of achieving them (1993) — link
- Risk management in enterprise resource planning implementation: a new risk assessment framework (2011) — link
- Extending the risk process to manage opportunities (2002) — link
- How to manage the risks you didn’t know you were taking (2014)
- Managing Overall Project Risk (2014)
- An Evaluation of Total Project Risk Based on Fuzzy Logic (2015) — link
- COMMENTARY ON THE INTERNATIONAL STANDARD ISO 31000–2009 “RISK MANAGEMENT. PRINCIPLES AND GUIDELINES” (2014) — link
- Risk assessment in new software development projects at the front end: a fuzzy logic approach (2016) — link
- Critical-Path Planning and Scheduling (1959) — link
- Project Management Methodology (2013) — link
- A new proactive approach to construct a robust baseline schedule considering quality factor (2015) — link
- Improving the risk quantification under behavioural tendencies: A tale of construction projects (2018) — link
- A generic heuristic for multi-project scheduling problems with global and local resource constraints (RCMPSP) (2018) — link
- Una nomenclatura unificada para problemas de programación de proyectos (RCPSP and RCMPSP) (2018) — link
- Portfolio Selection: Efficient Diversification of Investments (1959) — link
- A Mathematical Theory of Evidence (2020) — link
- Flexible resource management and its effect on project cost and duration (2018) — link
- An interactive risk visualisation tool for large-scale and complex engineering and construction projects under uncertainty and interdependence (2018) — link
- A review of methods, techniques and tools for project planning and control (2018) — link
- Improving Project Budget Estimation Accuracy and Precision by Analyzing Reserves for Both Identified and Unidentified Risks (2018) — link
- Time-cost tradeoff analysis with minimized project financing cost (2018) — link
- Risk identification and assessment in sustainable construction projects in the UAE (2018) — link
- A survey of hybrid metaheuristics for the resource-constrained project scheduling problem (2019) — link
- Time and cost contingency management using Monte Carlo simulation (2019) — link
- Risk Analysis Development of Solar Floating Power Plant in The Sea with Monte Carlo Method (2018) — link
- Reinventing Project Management: The Diamond Approach to Successful Growth and Innovation (2007)
- Project risk management of the construction industry enterprises based on fuzzy set theory (2019) — link
- Forecasting the Project Duration Average and Standard Deviation from Deterministic Schedule Information (2020) — link
- Portfolio scheduling: an integrative approach of limited resources and project prioritization (2020) — link
- Risk Management in Global CRM IT Projects (2020) — link
- Mean-conditional value at risk model for the stochastic project scheduling problem (2020) — link
- Cost Contingency and Cost Evolvement of Construction Projects in the Preconstruction Phase (2020) — link
- Prediction of simulated cost contingency for steel reinforcement in building projects: ANN versus regression-based models (2020) — link
- Cost Performance and Cost Contingency during Project Execution: Comparing Client and Contractor Perspectives (2020) — link
- A Survey on Integration of Optimization and Project Management Tools for Sustainable Construction Scheduling (2020) — link
- Project risk management from the bottom-up: Activity Risk Index (2020) — link
- A multi-agent based cooperative approach to decentralized multi-project scheduling and resource allocation (2020) — link
- Fuzzy-Based Multivariate Analysis for Input Modeling of Risk Assessment in Wind Farm Projects (2020) — link
- Stochastic risk analysis and cost contingency allocation approach for construction projects applying Monte Carlo simulation (2017)
- Measuring Time (2009) — link
- Against risk (1999) — link
- Project Risk Management: Processes, Techniques and Insights (1998) — link
- Innovation strategy (1990) — link
- A Mathematical Theory of Evidence (1976) — link
1 of 93 cited works are in the corpus; resolved via arXiv source bundles, Semantic Scholar and OpenAlex. Corpus-wide: 2518 linked papers.